PROGRESS


2009
Started planning for future of this site.
2014
Zoning permission granted.
2019
Registered as building site.
2024
Contract signed with construction company.
2011
Plan completed and church agreed.
2016 Building permit granted, communal tax paid.
2021
Preparing contract with construction co.
2024
Start of tearing down the old church building.
2025
concrete piles to reinforce the foundations.
2025
Digging construction pit.
2025
Forming of the underground garage.
Information on major points of progress during this project
-
We began examining our options for the existing building in 2008/2009. It was apparent that it needed a new roof, completely new electricity, new plumbing, and new central heating. In addition, the building only accommodates approximately 90 seats in the sanctuary, which forced us in 2014 to begin holding two services each Sunday morning to have enough space for everyone. Now we are even facing challenges with space in our second service.
-
Our initial intent was to extend the existing building; however, because of town planning, the building needed to be moved back 2.5m to allow for potential road expansion, which would not be possible with the existing sanctuary. It was apparent that there were only two options: (1) sell the current property and purchase another site, or (2) demolish and rebuild 2.5 meters back.
-
In 2011, the plan was completed and approved by the church members. We then had to complete all the planning processes and obtain zoning permission, permission from neighbors, and other necessary consents. Building permission was finally received in March of 2016.
-
After many meetings with the local governmental authorities, our project manager, our construction company, and church members, we agreed to register the property as a "building site in preparation" in April of 2019. We were given one year to prepare the site, and construction is planned to begin in March of 2020.
-
In 2024 we signed the contract with the building company ABV inženiring d.o.o.
-
In October 2024 we continued with works for tearing down the old building.
-
In January 2025, we began drilling holes and pouring concrete for piles, which are intended to reinforce the building's foundations.
-
In February 2025 we made concrete wall for garage.
We would kindly ask you to consider joining us in this project.

Getting ready to say goodbye to the old building, it has serviced us so well, there are so many memories.




Temporary facility (43 Celovška) found, rented (Dec. 2020), and renovated, ready for first services after Covid-19 restrictions.

Signing the contract.
October 2025

September 2025

August 2025

July 2025

June 2025

May 2025

April 2025

March 2025

February 2025

2024